Mill Creek Park Trail Phase 2

This project will see the construction of a nearly one mile-long non-motorized trail running adjacent to Mill Creek, extending from Mill Creek Park downtown to just north of Creekside Intermediate School along Baker Rd. The City received over $600,000 in grants to support this project, including grants from the Washtenaw County Connecting Communities Program and SEMCOG's Transportation Alternatives Program (TAP). 

Construction on this project began the week of March 23, 2020 with tree clearing. Construction was scheduled to be completed by June 30, 2020, however this schedule is subject to change due to the outbreak of COVID-19. There are no road closures expected with this project, but there may be some impacts to the existing trail where the new trail connects at the southernmost point of the boardwalk near the corner of Broad St. and Grand St.